0

I have a local testnet running and it works until the first lease period is up. Once the first lease period finishes the chain stops producing blocks. I am looking for an easy way to submit some extrinsics to extend the lease period for a parachain -- or would I have to do something more complex in order to accomplish this?

New contributor
IrradiatedMango is a new contributor to this site. Take care in asking for clarification, commenting, and answering. Check out our Code of Conduct.
1
  • Please clarify your specific problem or provide additional details to highlight exactly what you need. As it's currently written, it's hard to tell exactly what you're asking.
    – Community Bot
    Aug 6 at 7:54

1 Answer 1

0

IMHO, you could call sudo_schedule_parathread_upgrade first to onboard your chain. Then call force_lease to change the lease.

Your Answer

IrradiatedMango is a new contributor. Be nice, and check out our Code of Conduct.

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.